|
Fred Taylor Drive Widening
- $4.8M improvement to increase width to four lanes
- Included 4,400 ft. on Fred Taylor Drive, 1,000 ft. on Lane Avenue, and 600 ft. on Ackerman Road
- Lighted parking for 2,000 vehicles
- Addition of turn lanes with signalization
- Detention areas and storm sewers
|
|
- Improvement of 1.5 miles of minor arterial
- Includes new pavement, curb and gutter, replacing the existing 20-in. waterline, new storm sewer, and right-of-way plans for 325 parcels
- Involves 21 intersections and ADA compliant curb ramps at all corners
|
|
Wellston Industrial Access Road
- Recently completed $1,000,000 project
- Two-lane facility with a length of 6,500 ft.
- 1,000 ft. followed existing Township Road; with balance on new location
- Alignment studies done to avoid a small wetlands
|
|
FRA-161-16.75/LIC-161-0.00 - New Albany Expressway
- $46 M project completed in 1995
- 30 month design schedule
- 7.4 miles of 4- to 6-lane pavement
- 4 overpasses
- 11 bridge sites
- 16 separate bridges
- 3½ diamond interchanges
|
|
London Avenue (SR 38) and Ninth Street Intersection Improvements
- Completed in 2003
- Involved design of a new signal at stop-controlled intersection with high accident rate
- Plans developed to City of Marysville and ODOT standards
- New signal utilized existing right of way for all poles and components
|
|
Milford/Ninth/Collins Corridor Study
- Completed in 2003
- Corridor study to determine an alignment that would improve traffic flow in the area of Milford Road, Collins Avenue and Ninth Street
- Two parallel roadways connected midway and crossed under a former railroad; the railroad has ceased operation and the bridge over the roadway was removed
- Auditor’s mapping was used to produce two alternatives
- A report was generated including all data and figures
|
|
Harrisburg Pike Improvements (FRA-62-9.07)
- Began as a safety study for one mile curb and gutter section
- Involved preparing a Level 2 Categorical Exclusion Document
- Prepared plans for widening existing roadway from 2 to 3 lanes
- Included additional right turn lanes, four signalized intersections and small bridge replacement.
- Currently in Step 7 of ODOT’s new PDP-minor 10-step process
- Project is under an accelerated schedule to meet ODOT’s funding requirements
|
|
U.S. 33 in Logan County, Ohio
- From 1990-2000, provided engineering services for several projects along U.S. Route 33 for ODOT District 7
- Part of three separate projects packaged for sale
-
- Designed structure number LOG-33-15.96(R)
-
- ODOT District 7 designed the roadway
-
- Four-span continuous steel beam superstructure on reinforced concrete piers and abutments
- LOG-540-1.42 Interchange (Part II)
- $4,000,000 diamond interchange
-
- Addition of two lanes to existing U.S. 33 and two service roads
-
- One mile of reconstruction on SR540
-
- Extensive maintenance of traffic plans
- $1M project
-
- Prepared plans for Township Road 55 over U.S. 33
-
- Included approach roadways and necessary right-of-way
- Designed two new structures and rehabilitated two existing structures
-
- LOG-33-20.78 (R): fatigue analysis, replacement of all structural steel and widening of the piers
-
- LOG-33-21.09: modified substructure of existing three-span reinforced concrete slab and construction of a new concrete deck
- Conventional diamond interchange with extensive earthwork necessitated by the surrounding hilly terrain
-
- Plans included maintenance of traffic, and partial lighting
-
- Special study included in the right-of-way accommodated expensive residential access in the southwest quadrant
-
- Opened to traffic in 1996
-
- Cost was approximately $3.5 million
|
|
- Total length of mainline of 20 miles
- Project included four interchanges, roadway, lighting, and right-of-way design
- The SR 4 and SR 31 interchanges required complex phasing of collector-distributor lanes
|