Stormwater/Drainage Design Experience

FRA-670-3.17 Stormwater Outlet Impact Study

  • Study and stormwater analysis of storm flow between Neil Avenue and North High Street
  • Compared pump station to gravity sewer outlet to handle the increased storm flow due to additional traffic lanes on I-670
  • Gravity sewer was determined to be less costly to build and maintain

Twelfth Avenue Sewer Separation - Part II

  • $6.0 M project completed in 1997
  • Design for 2,200-feet of 14'x5' box sections constructed by cut and cover
  • Reconstructed pavement, curb and sidewalk on Twelfth Avenue
  • Required tunneling for more than 1,000 feet of 102" storm conduit
  • Extensive maintenance-of-traffic plans

Twelfth Avenue Sewer Separation - Part I

  • $750,000 project completed in 1992
  • Purpose of project was to alleviate severe flooding in the OSU campus area
  • Detailed plans and specifications to replace aging 108"  storm sewer
  • Project was a result of the OSU Area Stormwater Study prepared earlier by our firm

Stormwater Detention Basin and Sanitary Sewer Filter Screen Marysville Reformatory for Women

  • $170,000 project completed in 1991
  • Included a mechanical filter screen and electrical service to operate
  • Storm water retention basin retrofit

New Albany Expressway Stormwater and Drainage

  • ODOT’s single largest project during 1996
  • 7.4 miles of 4 to 6-lane pavements / 3-1/2 interchanges
  • Peripheral streets and roadways totaled 12.5 miles
  • Controlling stormwater required 6.7 miles of 6" to 60” conduit
  • Additional 35 miles of 4" and 6" underdrain required under the pavement
  • Also included roadway ditch analysis

Astor Ditch

  • $799,176 project completed in 1996
  • Improved 3,000 feet of stormwater ditch
  • Included detailing 5 pre-cast concrete sectional culverts

Franklin Main Sanitary Sewer

  • Trenchless rehabilitation of 1,600 ft. section of 30" round brick sewer on the OSU Main Campus with 30" CIPP Liner (11.0 mm)
  • University elected to improve the Franklin Main due to age (c. 1895), and recreation fields being constructed above it (ownership of sewer by City)
  • Analysis of existing sewer involved light cleaning and CCTV services
  • Provided design and  construction administration in 2003

Sanitary & Storm Sewer System Renovation Ohio Reformatory for Women

  • $2.1 M sanitary and storm sewer system improvement project at aging penal institution
  • Evaluation of manholes, sump pumps, and lift stations, and close circuit televising of the sanitary sewer system
  • CCTV inspection coupled with colored dyes to determine cross connections between the storm and sanitary sewers
  • Prepared construction plans and bid documents for rehabilitation
  • Emphasis on non-disruptive remedial repair such as relining

Waterline Design Experience

Sullivant Avenue Water Line Cleaning

  • Design completed in 2003
  • Cleaning and lining of 19,200 ft. of 20” water main
  • Includes replacing several defective water valves

Wexner Center Waterline The Ohio State University

  • $40,000 project completed in 1984
  • Development of construction plans for 20” waterline under College Road

OSU Utility Master Plan - Northwest Sector

  • $730,000 project completed in 1986
  • Development of utilities plan for future needs for the 700-acre site
  • Recommended a plan for 12,000 ft. of 8”, 10”, and 12” waterlines

Doherty Road - Feder Road Waterline

  • $340,000 project completed in 1983
  • 9,500 ft. of 12" waterline to service an area being supplied by individual wells

Oakland Park Avenue, Cleveland Avenue, and Gay Street Water Mains

  • $330,000 project completed in 1987
  • 3,900 ft. of 6" to 8" water lines to boost pressure and improve fire protection

Waterline Improvements in the Southwest Columbus Quadrant

  • $705,000 project completed in 1991
  • 13,400 ft. of 6" to 8" water lines at 15 locations to boost pressure and improve fire protection

Waterline Improvements in the Southeast Columbus Quadrant

  • $940,000 project completed in 1994
  • 9,400 ft. of 6" to 16" water lines at 21 locations to boost pressure and improve fire protection

Central Pressure District Waterline Improvements

  • $990,000 project
  • 11,940 l.f. of 12", 8" and 6" water line located on 13 streets
  • Alignment, reference points and topography were field surveyed for each location
  • New water lines provided cross-connections between streets to boost pressure to 119 service taps for individual residences

Central Waterline Replacement

  • $700,000 project completed in 1995
  • Project replaced 2" to 20" watermains

Waterline Replacement Columbus Developmental Center

  • $684,000 project completed in 1996-1997
  • Project accomplished in two phases
  • Replaced 9,700 l.f. of 6", 8" and 12" waterlines, installed meters, and replaced older services lines to the various facilities on the campus

Oval Restoration - The Ohio State University

  • Completed in 2003
  • Construction cost $558,000
  • Investigated alternative water sources for irrigation and modeled existing system with flow test data to determine proper size of piping and equipment
  • Designed waterline connection from main line to irrigation system
  • Designed meter, backflow preventer, and irrigation flow controller within the basement of adjacent building restoration project
  • Construction administration services included limited observation

Contact Us | About Us | Our Services | Career Opportunities | FTP Site | Current Projects

© 2006 Jones-Stuckey Ltd., Inc. All Rights Reserved.
2323 West Fifth Ave., Suite 160, Columbus Ohio, 43204
Phone: 614-486-0401 Fax: 614-486-1194